Dormitory

SINGAPORE

(ACCOMODATION)

A Quick turnaround was necessary to accommodate 600 workers at client's Production Facility at the height of the COVID 19 Pandemic. 

The Ancillary office needed to be turned into a Workers Dormitory Urgently.

CREDITS.

PLANNING TEAM.

HO SHU YUAN

TIMELINE

8 MONTHS FROM PLANNING TO COMPLETION

HIGHLIGHT

FAST TURNAROUND OF PROJECT FROM START TO FINISH

We were commissioned to design this space early after the entire building was built. Our new program included wide living room and kitchen, home theater, a master bedroom - and the most important feature: a rooftop swimming pool.

ABOUT.

AREA.

90,000 SQFT · 8,361 SQM

ROOMS.

45 ROOMS Across 9 FLOORS for 500 Workers

The challenge was to do all planning and start a project during the shutdown of the COVID 19 Pandemic. Meetings and all Government approvals had to be done all online and we did not know when work could start.

The moment workers were able to start work , some workers would start first , all under the rules of Social Distancing and with a limit on the amount of workers allowed on site 